I wonder if this ever happened. It would be fun to see the safety analysis for ultrasonic fuel cleaning of 16 discharged BWR fuel assemblies in a pool at Vallecitos. Maybe they pulled it off under 50.59.
Following is from this blog on August 25, 2007:
First BWR planning to ultrasonically clean fuel:
Quad Cities Unit 2
Planned Date: Spring 2004 Purpose: Dose rate reduction
*
Mock-up testing taking place at Vallecitos, 16 discharged assemblies
will be cleaned on a pre-trial basis in Fall 2003. Anticipate cleaning
first reload assemblies in Spring 2004.